โšก 30-sec brief: Two sites. Thaxton โ€” get TIA cost/timeline before you can answer Puckette Friday. FM 812 โ€” Lennar's infrastructure likely cuts your utility cost dramatically; verify with Mahoney. Bobak has TIA answers โ€” get him on a call today or tomorrow morning.

๐Ÿ—๏ธ Thaxton Corner

April 29 extension deadline
1
Get a real TIA number. You need cost + timeline from Mahoney to tell Puckette on Friday. Don't leave without a range.
2
Confirm CP5 is on track. End of week โ€” all Sean's items in (DT lane, depths, dumpsters, gym, rear alley).
3
Get Bobak on a call. Ask Tyler: "Can Bobak join today or can we do 30 min with him before Friday?" His TIA answers are ready.
Questions โ€” ask in this order
  • 1"TIA redo โ€” what does it cost and how long does it take? Give me a range."
  • 2"The current Thaxton driveway is 600ft from the corner. For our QSR lots to work, we need it closer. What's feasible? What's TxDOT's minimum spacing here?"
  • 3"Can we get a second driveway on Thaxton Road? What's the process?"
  • 4"The existing TMA has a $400K+ mitigation obligation. It was based on M/I Homes' prior concept โ€” not our program. Is there an argument that number changes with a new TIA?"
  • 5"CP5 โ€” on track for end of week? DT stacking lane, lot depths, gym option, dumpsters, rear alley on Lot 6 โ€” all in?"
  • 6"When is the Thaxton SIR coming? We need it before May 4."
  • 7"Can Bobak Tehrany join this call or get on a quick call before Friday?"
Decision you're making today: Do you have enough to know whether to extend on April 29? TIA cost + CP5 quality are the two inputs. Get both today.

๐Ÿ›ฃ๏ธ FM 812

SERs signed โœ…
1
Understand the Lennar impact. NEW Lennar is building a 16" water main and 24" wastewater interceptor (4ร— oversized) along FM 812. Does this eliminate BBM's utility extension cost?
2
Get the TxDOT ROW answer. Still the critical unknown. If TxDOT is taking ROW along FM 812, it could clip the site. Mahoney needs to escalate this.
3
Understand what BBM still needs to build. If Lennar's trunk is passing adjacent, what's BBM's remaining utility cost โ€” tap + lateral, or something more?
Questions โ€” ask in this order
  • 1"Lennar is building a 16-inch water main and 24-inch wastewater interceptor along FM 812 for the Wong Tract. How close does that infrastructure pass to our property boundary? Can we tap directly into it?"
  • 2"If we can tap into Lennar's infrastructure โ€” what does BBM's actual utility cost become? Ballpark."
  • 3"TxDOT ROW โ€” what's the status? Have you been able to reach the project manager? What specifically are they acquiring and does it affect our site?"
  • 4"What does FM 812 access look like โ€” number of driveway cuts, TxDOT spacing requirements, permit process and timeline?"
  • 5"Any other flags from the SIR that change the economics of this deal?"
Decision you're making today: Does the utility picture โ€” with Lennar's infrastructure โ€” make FM 812 viable? If Lennar eliminates the trunk extension cost, the math changes significantly.

๐Ÿšฆ Bobak Tehrany โ€” Get Him On A Call

Has answers ready

Bobak reviewed the TMA and CP4 and texted that he's ready. His input is the most valuable thing you can get before Friday's Puckette call โ€” he can tell you the TIA cost, whether the $400K mitigation can be renegotiated, and what's actually feasible on the driveways.

Bobak Tehrany, P.E. BOE Services ยท bobak@boeservices.com ยท 737-301-2128
๐Ÿ’ก Ask Tyler at the meeting: "Can we get Bobak Tehrany on this call or do a quick 30-minute call with him before Friday morning?"

โœ… Before You Leave This Meeting

๐Ÿ“ž Friday 10:30am CT โ€” Heather Puckette Call

Heather needs a written summary of BBM's development plans + how the TMA impacts them, so she can negotiate with Seller's counsel. You need Bobak's input before you can give her real numbers.

What Heather needs from you
  • โ†’BBM's development program: how many lots, what uses, where the driveways go
  • โ†’TIA redo cost + timeline (get from Mahoney/Bobak today)
  • โ†’Why the existing $400K TMA obligation needs to be renegotiated
  • โ†’What changes to the TMA BBM requires to proceed
Zoom link: https://kutakrock.zoom.us/j/87039909753 ยท Meeting ID: 870 3990 9753

๐Ÿ“ž Quick Contacts

Tyler BoykinMahoney Engineering ยท 737-270-7310 D ยท 512-574-9636 M
Bobak TehranyBOE Services (Traffic) ยท 737-301-2128 D ยท bobak@boeservices.com
Heather PucketteKutak Rock ยท 303-292-7855 ยท Fri 10:30am CT
Daniel MahoneyMahoney Eng ยท 512-596-2579 D