PSA milestones, feasibility deadlines, and critical dates across all active deals
| Deal | Entity | Milestone | Date | Days Until | Status | Owner |
|---|---|---|---|---|---|---|
| Thaxton Corner | BBM | 🔴 Title & Survey Objection Letter Due | Apr 2, 2026 | 2 days | 🚨 URGENT | Heather Puckette |
| Thaxton Corner | BBM | 🔴 ALTA Survey Deadline (~60 days from ED) | Apr 6, 2026 | 6 days | 🚨 URGENT | BBM / Surveyor |
| Thaxton Corner | BBM | 🟡 Seller Deadline to Cure Title Objections | Apr 17, 2026 | 17 days | ⚠️ Watch | Seller / Kutak Rock |
| Thaxton Corner | BBM | 🟡 Extension Notice #1 (≥5 days before May 4) | Apr 29, 2026 | 29 days | ⚠️ Decision | BBM / Kutak Rock |
| Thaxton Corner | BBM | ⬜ $10K Extension Fee to Seller (if extending) | May 1, 2026 | 31 days | Conditional | BBM Treasurer |
| Thaxton Corner | BBM | 🟢 Initial Feasibility Period Expires (90 days) | May 4, 2026 | 34 days | 🟢 On Track | BBM Team |
| Thaxton Corner | BBM | 🟢 Closing (if no extension — 30 days after feasibility) | Jun 3, 2026 | 64 days | 🟢 Target | Kutak Rock |
| Slaughter Park Preakness | JAK | 🟢 Closing (6-mo NRP extension from Mar 10, 2026) | ~Sep 10, 2026 | ~163 days | 🟢 On Track | NRP / JAK |
| Thaxton Corner | BBM | ⬜ End of Extension #1 Feasibility (+60 days) | Jul 3, 2026 | 94 days | Conditional | BBM / Kutak Rock |
| Thaxton Corner | BBM | ⬜ End of Extension #2 Feasibility (+60 days) | Sep 1, 2026 | 154 days | Conditional | BBM / Kutak Rock |
| Thaxton Corner | BBM | ⬜ Final Outside Closing (30 days after max feasibility) | Oct 1, 2026 | 184 days | Conditional | Kutak Rock |
| Kohlenberg / NB | BBM | LOI / Negotiation Stage — No PSA yet | TBD | TBD | Pre-PSA | BBM Team |
| FM 812 / Wong Tract | BBM | Phase II Environmental Pending — Closing TBD | TBD | TBD | ⚠️ Pending | Environmental / BBM |
| Mayfair BTR | JAK | NRP JV Diligence — No hard PSA deadlines yet | TBD | TBD | JV Diligence | Novak / JAK |