๐Ÿค– Atlas Notes
FM 812 is under contract in the Austin ETJ. Mixed-use MF + Retail concept. Austin ETJ provides more flexible entitlement path than City of Austin. Watch city annexation risk as Austin ETJ has been shifting. This is a BBM project โ€” Craig Biggar involved.

๐Ÿ˜๏ธ Lennar / Millrose โ€” Key Utility De-Risk: Lennar is actively building homes on the tract immediately behind our site. The land is held by Millrose Properties โ€” Lennar's subsidiary that holds land and does horizontal development work before handing off to Lennar for homebuilding. Lennar is responsible for bringing water and wastewater infrastructure near our site, which meaningfully de-risks our utility situation and could reduce our infrastructure costs substantially.
๐Ÿ“‹ Craig's Action Items
โšช Pending Review due diligence materials โ€” engineering and title Ongoing
โšช Pending Coordinate with civil engineer on concept plan TBD
๐Ÿ“ Project Stage
โœ… Contract
โ†’
๐Ÿ“ Due Diligence
โ†’
Entitlement
โ†’
Financing
โ†’
Construction
โšก Action Items ๐Ÿค– March 30, 2026
ActionOwnerDueStatus
Complete due diligence โ€” survey, title, environmental John / Craig Ongoing ๐ŸŸก In Progress
Concept plan for MF + Retail layout John / Craig / Engineer TBD โšช Pending
๐Ÿ’ฐ Costs & Expenses ๐Ÿค– March 30, 2026
CategoryItemBudgetActualNotes
LandFM 812 AcquisitionSee trackerSee trackerUnder contract
EngineeringCivil / Concept PlanSee trackerSee trackerIn progress
LegalPSA / Title / LegalSee trackerSee trackerIn progress
Hard CostsMF ConstructionTBD$0Post-entitlement
Hard CostsRetail Pad ConstructionTBD$0Post-entitlement
TOTALSee Cost Tracker spreadsheet
๐Ÿ’ก Full cost detail in the FM 812 Cost Tracker spreadsheet.
๐Ÿ“ FM 812 Project Files ๐Ÿค– March 30, 2026
๐Ÿ“Š
FM 812 Project Tracker
BBM ยท Excel ยท OneDrive โ€” master tracker
๐Ÿค– Last updated by Atlas ยท March 30, 2026
๐Ÿ“‚ Open Document โ†’
๐Ÿ’ฐ
FM 812 Cost Tracker
BBM ยท Excel ยท OneDrive โ€” budget & actuals
๐Ÿค– Last updated by Atlas ยท March 30, 2026
๐Ÿ“‚ Open Document โ†’
๐Ÿ“… Project Timeline ๐Ÿค– March 30, 2026
TBD
Concept Plan Completion UPCOMING
MF + Retail layout finalized with civil engineer.
TBD
Entitlement / Permitting UPCOMING
Austin ETJ permitting for multifamily and retail pads.
TBD
Financing / Equity Raise UPCOMING
Construction financing and equity structuring.
TBD
Construction Start UPCOMING
MF + Retail pad construction begins.
Past Events
2025โ€“2026
PSA Executed โ€” Under Contract DONE
FM 812 under contract. BBM 2025, LLC buyer. Due diligence in progress.
2025
Deal Identified DONE
FM 812 identified as MF + Retail development opportunity in Austin ETJ.
๐Ÿ’ฐ Deal Economics โ€” GP/LP ๐Ÿค– Pending info needed
๐Ÿ“‹ Action Item: Provide Deal Economics Info to Build This Section
Atlas needs the following to build the full GP/LP waterfall analysis for this project:
  • LTV% on land loan
  • LP preferred return %
  • GP/LP promote split
  • GP equity %
  • Land use plan (MF + retail breakdown)
  • Target lot/pad sale pricing
  • Estimated soft costs / dev timeline
๐Ÿ“ฑ Trigger: Send Atlas the info via Telegram and I'll build the full analysis immediately.
๐Ÿ‘ฅ Key Contacts
Craig Biggar
BBM 2025, LLC ยท Partner
Due diligence & project oversight
Kent McNeil
BBM 2025, LLC ยท Partner
Deal structuring & financing
John Burns
BBM 2025, LLC ยท Principal
๐Ÿ“ž 512.633.1008